A situação
A Serbian new-energy EPC company needed battery swap cabinet structures and vehicle bracket assemblies. Their previous supplier misread the drawings, the sample was reworked three times, and lead times were unpredictable.
O que fizemos
We reviewed the drawings and confirmed the critical tolerances with the buyer's engineer, then selected a workshop with existing new-energy project experience. First article confirmation and sign-off happened before batch production, and we tracked the full production flow and supervised loading.
O resultado
The sample was approved on the first submission. The batch was completed and shipped on schedule, and the customer passed local project acceptance.