CNC MACHINING · Serbia

Battery swap station frames for a Serbian EPC contractor

Three sample reworks with the previous supplier — first article approved first time, batch delivered on schedule.

A situação

A Serbian new-energy EPC company needed battery swap cabinet structures and vehicle bracket assemblies. Their previous supplier misread the drawings, the sample was reworked three times, and lead times were unpredictable.

O que fizemos

We reviewed the drawings and confirmed the critical tolerances with the buyer's engineer, then selected a workshop with existing new-energy project experience. First article confirmation and sign-off happened before batch production, and we tracked the full production flow and supervised loading.

O resultado

The sample was approved on the first submission. The batch was completed and shipped on schedule, and the customer passed local project acceptance.

Envie-nos um desenho

Basta um arquivo STEP, um PDF ou uma foto da peça. Em 48 horas você recebe uma pré-seleção, uma comparação detalhada e um cronograma realista.